Installing a Walk-Through Metal Detector: Six Steps and Eight Acceptance Checks

2026.11.16

Short answer

A walk-through detector is a single integrated unit: six steps and about twenty minutes to assemble. But assembled is not the same as accepted. Eight checks decide whether the gate is usable, and two of them — no alarm on an empty pass, and a clean alarm on the sample — determine whether any later tuning means anything.

1. Check the box first

  • Control unit with display and main board
  • Left and right detection panels (marked — fitting them the wrong way round degrades sensitivity)
  • Zone indicator columns
  • Infrared sensors and internal wiring
  • Waterproof foot covers
  • Hex key, eight sets of bolts, manual, warranty card

2. Assembly in six steps

  1. Unpack and lay out: control unit face up, panels on either side as shown in the diagram
  2. Bolt the panels to the control unit: bolts and nuts on both sides, tightened fully
  3. Connect the probe leads: each panel lead goes to its matching socket on the main board and must be fully seated — a loose connector is the most common cause of "not counting" and erratic sensitivity later
  4. Fit the top cover: four screws, tightened
  5. Stand it up: raise the gate to vertical and move it to position
  6. Power on: connect the mains lead at the rear; the unit runs a self-test

The design is integrated, so a practised team can assemble or dismantle a gate in about twenty minutes.

3. Site check before any tuning

  • 2 m from fixed large metal — aluminium or stainless frames, reinforced walls
  • 5 m from movable large metal — roller shutters, steel doors, lifts, vehicles
  • 1–2 m from electrical interference — control cabinets, radios, inverters, large motors
  • Never in a draught: wind moves the panels and causes false alarms
  • Flat, rigid floor so the gate does not rock when people walk past

4. The eight acceptance checks

#CheckPass condition
1Vertical and stableStands vertical, does not rock when pushed, foot covers fitted
2Panel orientationLeft and right fitted per the markings
3Probe leadsBoth seated; a light pull does not detach them
4Self-testReaches the working screen after about one minute, no errors
5People countingSingle pass increments by one; ten consecutive passes count correctly
6Empty passA person carrying no metal passes without an alarm
7Sample passThe chosen sample alarms, with the correct zone indicated
8Alarm resetAfter the alarm stops, the next person passes normally without a repeat alarm

Checks 6 and 7 are the reference points for sensitivity: no alarm when empty, a clean alarm on the sample. If either fails, do not start changing parameters.

5. Reference specifications

ItemValue
Passage size1990 × 700 × 500 mm (H × W × D)
Overall size2220 × 815 × 500 mm
Net weightabout 60 kg
Power220–240 V, 50/60 Hz
Consumptionunder 30 W
Operating temperature-25 °C to +55 °C
Throughputover 60 people per minute
ConstructionPVC composite panels, waterproof foot covers

6. The four mistakes that actually happen

Probe lead not seated. Shows up as "does not count" or "one zone never alarms". Pull each lead lightly after assembly.

Panels swapped. Invisible from outside, but transmit and receive are reversed and sensitivity drops noticeably.

Installed in a draught or beside a roller shutter. The gate moves, the alarm never settles. No parameter fixes this.

Uneven floor. The four feet carry different loads, the gate sways slightly as people pass, and the result is an intermittent alarm that is very hard to diagnose.

7. Day-to-day care

  • Do not knock or bump the panels — it causes false alarms and can damage them
  • Clean with a cloth dampened with water or alcohol; no other solvents
  • The enclosure contains high voltage; only qualified staff should open it
  • Keep the warranty card; service within the warranty period requires it
  • Change the factory settings password and record who holds it

FAQ

It alarms constantly after installation. Run check 6 first. If an empty pass alarms, it is siting or stability, not sensitivity — measure the distances, check for draughts, check the floor.

It alarms but does not count. Infrared problem: check the panel leads, then look for interference near the sensors (cameras, remote controls, direct sun), then replace the sensor.

Can it be installed outdoors? The panels are weather-treated, but a canopy is strongly recommended, and the sensors must be out of direct sun and draughts.

Do we need the factory to commission it? The checklist is usually enough. If three or more of the eight checks fail, call the factory — it is almost always an installation issue.

Related

How to set detector sensitivity · Choosing between metal, phone, precious-metal and temperature gatesDetector maintenance checklist

Products: FJ-WT18 metal detector gate · copper, silver and gold gate · mobile phone detection gate

Want advice for your own site? Tell us what you inspect, the daily volume and the site conditions — we will propose an approach before proposing a product.