X-Ray Scanner Acceptance: Delivery, Installation, Performance and Training

2026.11.16

Short answer

Awarding the contract is the start, not the end. Delivery, installation and performance acceptance each need a written record, and training must happen before performance acceptance — because the buyer's own operators have to run the tests, and untrained operators cannot even place the test pieces correctly.

Stage 1: delivery acceptance

  • Check model, serial number and accessory list against the contract
  • Inspect for deformation, scratches and corrosion
  • Count the documents: manual, certificate of conformity, warranty card, test report, packing list
  • Count tools and spares: lead curtains, bolts, hex key, fuses
  • Confirm transport restraints are removed before power-on

Photograph and document any discrepancy on the spot. Raising it after installation makes responsibility almost impossible to establish.

Stage 2: installation acceptance

Position and layout. Installed as drawn; roller tables long enough; the queue does not block a passage.

Power and earthing. Stable voltage, dedicated circuit, compliant earth resistance. Poor earthing shows up later as image noise and intermittent faults.

Radiation protection. Curtains intact, door interlocks working, warning labels present. Measure the cabinet surface and operator position with a survey meter.

Environment. Ventilation, heat and humidity within specification; not next to heat sources or heavy electrical equipment.

Stage 3: performance acceptance (the important one)

ItemMethodPass criterion
PenetrationStandard steel step wedgeMeets the contracted figure
Wire resolutionStandard wire pair cardMeets the stated AWG
Spatial resolutionTest card, horizontal and verticalMeets the stated millimetres
Image qualityCompare with real baggage samplesCorrect colour classification, sharp edges
ThroughputTime a continuous runMeets the stated units per hour
LeakageSurvey meter at 5 cm from the cabinet≤1 μSv/h

Both parties must agree the test pieces and record their identity and the pass criteria in the acceptance report. Most disputes come down to "we were not using the same test piece".

Train before acceptance, not after

Many projects leave training to the end, then discover nobody can operate the machine during acceptance and the vendor runs the tests — which means nothing was verified.

  1. Installation complete → two-hour basic operation training by the vendor
  2. Operators run the machine independently for a day
  3. Performance acceptance executed by the buyer's operators; the vendor records results
  4. After acceptance, four hours of advanced training: image reading, common faults, emergency handling

Keep attendance sheets and assessment records so training can be traced when staff change.

Typical disputes

Penetration short of the figure. First confirm the test piece matches the contract, then the method — was packaging included, was the beam angled?

Throughput short. Usually operator unfamiliarity or roller-table flow, not the machine. Re-test with an experienced operator.

"Image quality feels poor." The contract should specify objective measures (resolution, penetration) rather than subjective descriptions.

Training not delivered. Require a training outline and assessment record as an acceptance attachment.

Payment milestones

Tie the final payment to "performance acceptance passed and training completed", not to delivery. Delivery proves the goods arrived, not that they work.

FAQ

Should we use a third party? For large or regulated projects, yes — an accredited body can test radiation and performance, and the report supports filing with the regulator.

What if acceptance fails? List the non-conformities in writing with a rectification deadline and a re-test method. Never settle it verbally, and do not sign off before rectification.

How many people should be trained? At least three, including one supervisor, so a resignation does not leave the site unable to operate.

Related

Writing the tender specification · Daily maintenance checklist

Products: 5030C dual-energy scanner · 8065C large tunnel scanner

Image storage and traceability

Want advice for your own site? Tell us what you inspect, the daily volume and the site conditions — we will propose an approach before proposing a product.